Piqua City Commission Regular Meeting
-
Authorize Fishbeck engineering agreement for I-75 Exit 78 Master Plan, Phase I ($1,985,000)
Authorizes the City Manager to enter into an agreement with Fishbeck for engineering services on the I-75 Exit 78 Development Area Master Plan Project — Phase I, at a total of $1,985,000. The Exit 78 area is the corridor where the J5 / Project Klondike datacenter site is located, and this engineering work is part of the public infrastructure planning that the project later relies on.
Passed 4–0- Yea
- Vetter, Hohman, DeBrosse, Lee
- Absent
- Simmons